Pagkukumpuni sa Navotas flood gate, sisimulan na sa Agosto; kabuuang pinsala, sisingilin sa nakasirang barko | 24 Oras

  • 2 months ago
Sisimulan na sa Agosto ang paghuhukay sa naipong burak at pagkukumpuni sa nasirang flood gate sa Navotas.


24 Oras is GMA Network’s flagship newscast, anchored by Mel Tiangco, Vicky Morales and Emil Sumangil. It airs on GMA-7 Mondays to Fridays at 6:30 PM (PHL Time) and on weekends at 5:30 PM. For more videos from 24 Oras, visit http://www.gmanews.tv/24oras.

#GMAIntegratedNews #KapusoStream

Breaking news and stories from the Philippines and abroad:
GMA Integrated News Portal: http://www.gmanews.tv
Facebook: http://www.facebook.com/gmanews
TikTok: https://www.tiktok.com/@gmanews
Twitter: http://www.twitter.com/gmanews
Instagram: http://www.instagram.com/gmanews

GMA Network Kapuso programs on GMA Pinoy TV: https://gmapinoytv.com/subscribe

Category

🗞
News
Transcript
00:00Floodgates in Navotas will be broken in August.
00:07It is expected to end soon to avoid high water levels in Navotas and Malabon this rainy season.
00:13Joseph Moro was there.
00:21The barge was forced to enter the North Navotas Navigation of Floodgate on June 7,
00:26even though it was approved due to the low tide.
00:29This resulted in the destruction of the floodgate.
00:31Some parts of its lifting arms were damaged and other parts were damaged as well.
00:37Because the navigational gate controls the water
00:40that enters the waterways of Navotas and Malabon,
00:43it is more likely that some areas will be flooded, especially when the tide is high.
00:48It is a major component of the Kamanawa Flood Control Project.
00:53Even if the dike and the pumping stations are there,
00:56if the navgate is broken, the water will really enter.
01:01The rainy season that threatens flooding in Navotas and Malabon is the reason for the construction of the navigational gate.
01:10In August 2, the dredging of the debris collected below will begin
01:14before the construction of the navigational gate itself.
01:18It is time to find out the outcome of the construction of the navigational gate.
01:20It will be brought to the company of Barcong Sumira here.
01:23Hopefully by August 17, it will be operational again.
01:27In the next two weeks, of course, it can be affected by the weather,
01:33if there is a storm coming in.
01:36We're keeping our fingers crossed that during the repair, there will be no weather disturbance.
01:43The local government of Navotas and Malabon hopes that the navigational gate will be completed immediately
01:49before the rain stops.
01:51As of now, in Malabon, there are up to 3,000 residents in four barangays affected by the flood.
01:57Sometimes, water reaches the city hall.
02:00If there is a storm, it will be doubled.
02:03Because even the other streets that are not flooded yet, there will be excess water.
02:10In Navotas, there were four to five barangays flooded at first,
02:14but the barangay Tanza was the most affected if the navigational gate is there.
02:18Hopefully, it won't happen again.
02:21But if the storm follows, there will be more affected.
02:27Pumping stations are working again to help in reducing the flood.
02:32For GMA Integrated News, Joseph Morong, Tutok 24 Horas.
02:40For GMA Integrated News, Joseph Morong.