Pagbubukas ng Edsa-Kamuning Flyover, inaasahang mapapaaga ayon sa DPWH

  • 2 months ago
Pagbubukas ng Edsa-Kamuning Flyover, inaasahang mapapaaga ayon sa DPWH

Transcript
00:00Let's look at the latest updates on the retrofitting of the Camuning Flyover in Quezon City.
00:05Vel Custodio has a live report, Vel.
00:10Rise and shine, Dayan.
00:12Good news for the motorists who are passing through Edsa Camuning.
00:16It is expected that the opening of the Edsa Camuning Flyover will be early
00:20for all types of vehicles.
00:22According to the Department of Public Works and Highways, National Capital Region.
00:28Travelers who pass through Edsa Camuning every day are happy
00:33with the possibility that the opening of the Edsa Camuning Flyover will be early.
00:38It's better for the motorists,
00:44for the resorts,
00:47because the volume of traffic is increasing.
00:49Until then, there's traffic everywhere.
00:52It's better to open it early.
00:55It's better for everyone.
00:57Anytime, every day, always.
00:59It's hard for me to pass through.
01:01The part where the Edsa Camuning Flyover was closed in May will be old
01:06for the bi-phase retrofitting.
01:08Only the Edsa Bus Carousel can pass through now.
01:12At the moment, the bottom of the Camuning Flyover is being repaired
01:15and the deck slab is being replaced.
01:17The reason why we closed the deck slab
01:24is because we are replacing the deck slab.
01:34The initial target date is October
01:36to finish repairing the lower part of the Edsa Camuning Flyover.
01:41But as of now, we can see that our accomplishment is
01:46we are expecting to complete the deck slab of the Edsa Camuning Flyover
01:55before the end of August instead of October.
02:00That's why it's possible that the opening of the closed road
02:04in the so-called Tulay will be early in the first week of September.
02:07Once the Camuning Flyover is opened,
02:10the retrofitting will be done on the upper part of the Magallanes Flyover.
02:14The Department of Public Works and Highways, National Capital Region
02:18was only given the permit to close the road
02:20for the operation of the retrofitting of the Magallanes Flyover
02:23every 11 p.m. to 4 a.m.
02:26While it will be open for vehicles to pass through in the next few hours.
02:30The construction of the Guadalupe Bridge was also postponed
02:34before the end of the year.
02:36Only a few flyovers in the 14 Tulay in NCR are in critical condition
02:41and may collapse if the Big One collides
02:44according to the study of the Japan International Cooperation Agency or JICA.
02:49For the traffic update, the traffic flow in Edsa Camuning is still wide towards the northbound
02:56while the traffic flow is slowing towards the southbound,
03:00especially towards the service road.
03:02Travelers should remember to bring gas in the rain
03:07because it is expected to rain for today.
03:11Back to you, Diana.
03:13Thank you very much, Vell Custodio.