डूंगरपुर के चीखली में बन रहा संगमेश्वर हैंगिंग ब्रिज का कार्य अटक गया है. ठेकेदार को 33 करोड़ का ही भुगतान किया गया है.

Category

🗞
News
Transcript
00:00The biggest bridge in our area, Bedua, was sanctioned with a cost of Rs. 125 crores.
00:08It was in the 2016 budget announcement.
00:11The work was supposed to be completed by 2020.
00:15But due to the lack of budget, this work is not being completed.
00:19The budget of Rs. 14 crores is still pending.
00:27To complete this work, Rs. 34 crores will be required.
00:32But the government is not paying attention to this.
00:35Be it the central government or the state government or the government of Double Engine,
00:39our Mandgat Dham is the centre of faith.
00:42When the construction of this bridge began, the people of this area were very happy.
00:48They were very happy that the bridge is being built on this river.
00:54So, with the construction of this bridge, we will be able to reach the centre as soon as possible.
01:00The construction of this bridge was not completed in December.
01:03Because it has not been paid since July.
01:06The running bill is Rs. 14 crores.
01:09And there is a payment of Rs. 18 crores for the excavation.
01:13The work that could be completed in December has been completed by 93%.
01:20And if the payment is received now, it will be completed by March.
01:25The running bill is Rs. 14 crores.
01:27It is pending since July.
01:29And there is a pending payment of Rs. 18 crores for the excavation.
01:33The total payment is Rs. 33.8 crores.