Hutama Karya Infrastruktur mempercepat pengerjaan jalan tol Padang-Pekanbaru Seksi Padang-Sicincin sepanjang 36,6 kilometer menjelang Ramadan.
Transcript
00:00PT Hutama Karya continues to speed up the construction of the new Padang-Pekan toll road,
00:06Padang-Sicin-Sin section.
00:08When tested functionally at Christmas 2024 and the new year 2025.
00:14Director of Operational 3 PT Hutama Karya, Kon Joro, in the Padang-Paryaman regency,
00:20said on Thursday, January 16,
00:22that overall physical work has reached 99%,
00:26only a few points of work are left.
00:30In addition, PT Hutama Karya also continues to speed up the rest area process,
00:36while waiting for the test results and operating certificates issued by the relevant institution.
00:42After the test results, the operating certificate will be issued.
00:46We hope that at the end of January or early February,
00:50the operating certificate can be issued.
00:53The people of West Sumatra, especially in Padang,
00:56can enjoy before the fasting month,
00:58the Padang-Sicin-Sin toll road for the whole year.
01:01So on Eid al-Fitr, it's already working?
01:04Yes, it's already available.
01:06Both roads, sir?
01:07Both.
01:09Moreover, Kon Joro ensures that the construction of the new Padang-Pekan toll road,
01:13Sicin-Sin-Bukit Tinggi section,
01:15is still in accordance with the initial scheme planned earlier.
01:18Because until now,
01:20the party is still doing research,
01:22especially on land conditions,
01:24costs, and social issues,
01:26which is estimated to take 6 months to 1 year.
01:31Meanwhile,
01:32Andrei Rosiade, Deputy Chairperson of the 6th DPRRI Commission, said
01:36the issue arose because there is a concern from the Pemprok Sumbar
01:40related to land liberation,
01:42which should be taken seriously by the local government.
01:46Andrei said,
01:47the continuation of the construction of Sicin-Sin toll road, Bukit Tinggi,
01:50is waiting for the technical guidance from the central government,
01:53where the project will use the funding from state capital participation or PMN.
01:59If it is agreed,
02:01PMN 2026, PMN is state capital participation,
02:04in 2026,
02:06automatically later,
02:08at the end of 2026,
02:10HK can work.
02:12If this note is agreed by the government,
02:15then we can execute from Sicin-Sin to Bukit Tinggi.
02:19The value is Rp. 60 trillion,
02:21Rp. 20 trillion is a contribution from JK,
02:24Rp. 40 trillion later,
02:25will be won by HK to build the toll road.
02:29Andrei insisted,
02:30the toll road of Sicin-Sin-Bukit Tinggi section is a priority.
02:34Considering the access of the national road across Sumatra,
02:37it is also one of the main traffic jams in Renah Minang
02:41that is difficult to solve,
02:42especially during the holiday period.
02:45From Padang Pariaman, West Sumatra,
02:47Fandi Ogari, Antara News Agency, Muartaka.