00:00We have been waiting for this bridge since 2020, we notified the DM sir and it has been more than 3 years
00:07But we saw what happened to this bridge, crores of rupees were looted in the name of bridge repair
00:12And today our heavy vehicles, scooters, all the vehicles here have been shut down
00:19There are only 6 vehicles coming from the top of the bridge
00:22Then what did the EDA ring tell us?
00:24They told us that we will have to cross Ghatal, and the 10 km distance from Mithilapur to Kharagpur will be 160 km
00:30Suddenly, that road, without our knowledge, shut us down
00:38They have shut down 16 tons of vehicles, which means your 6 vehicles will not go there
00:42So today we are giving road tax, toll tax, insurance to the government
00:47The government is asking us to do everything
00:49But the government is not giving us the road tax that we are supposed to get
00:53We have come here today and you don't know about this bridge
01:00I think there is a circle here, or the EIA engineers have blocked this bridge
01:05Today, you know, we want to tell the officials of the administration or the engineers
01:11Today, a 6-seater vehicle has a capacity of 19 tons
01:15That means the load of each tyre is 3.26
01:19And our 7-seater vehicle has a load of 2.92
01:25That means the load of that vehicle is less on this bridge
01:29So we are not able to find out why this bridge is being shut down
01:35There was an inspection from 6.30
01:38There was a load test with a load vehicle, but nothing happened to the bridge
01:41This is due to some invisible reason
01:43Maybe they have made a deal with some NH or some toll company
01:47That more toll vehicles will go there, so they will shut it down
01:49There is some game here
01:51And they have shut down this bridge
01:53And where there is an ancient city of North and South Bengal
01:57It has been 3 years
01:58This is a fact, when there is death in Janmala
02:02They are telling us to go to Kolkata
02:04There we will have to pay 3,000 rupees toll tax and 14,000 rupees diesel
02:08Today, from Medinapur to Khadagpur
02:10Today, the distance from here to Kolkata is 10 km
02:13That is 280 km
02:14That means we have to pay 14,000 rupees toll tax and 2,000 rupees diesel
02:19Apart from this, it will take us 3 days
02:21We are not able to accept this
02:23Today, we have been arrested by the truck drivers
02:25We are questioning the administration
02:28If the administration does not listen to us
02:30We will shut down the bridge with all the trucks we have
02:35And we will make the city unmanageable