PT PLN (Persero) melalui sub holding PLN Indonesia Power berkomitmen melakukan pengelolaan pembangkit listrik ramah lingkungan secara berkelanjutan. Salah satunya diwujudkan melalui Pembangkit Listrik Tenaga Panas Bumi (PLTP) Kamojang, Kabupaten Bandung, Jawa Barat. Tak hanya memproduksi listrik bersih, PLTP Kamojang juga menjadi produsen hidrogen hijau melalui Green Hydrogen Plant (GHP).

Category

📺
TV
Transcript
00:00PT PLN Persero continues to stimulate the management of renewable electricity in the environment continuously.
00:05One of them is through the earth heat energy electricity generator or PLTP Kamojang located in the Bandung regency.
00:12PLN claims that PLTP Kamojang not only produces clean electricity, but also becomes a green hydrogen producer.
00:19PT PLN Persero continues to stimulate the management of renewable electricity in the environment continuously.
00:26One of them is through the earth heat energy electricity generator or PLTP Kamojang located in the Bandung regency.
00:31Not only does it produce clean electricity, PLTP Kamojang also becomes a green hydrogen producer through Green Hydrogen Plant or GHP.
00:38Not only does it produce clean electricity, PLTP Kamojang also becomes a green hydrogen producer through Green Hydrogen Plant or GHP.
00:45Green Hydrogen Plant or GHP.
00:48The specialist in the management of the business unit of the Kamojang PLN Indonesia Power, Iwan Setiono, said
00:57The step of producing this green hydrogen is done by PT PLN Persero to develop environmentally friendly energy
01:03in line with the achievement of the Net Zero Emission target in 2060
01:08where the Green Hydrogen Plant is expected to be one of the sustainable energy solutions in the future.
01:15The result of this green hydrogen even enters the Hydrogen Leafling Station in Senayan.
01:22Iwan explained that the geothermal or earth heat energy produced by green hydrogen has a large business potential in Indonesia.
01:33It was said earlier that this hydrogen plant uses condensate water left from the cooling process of the cooling tower
01:41where the cooling tower uses a closed circuit.
01:44So, the water produced by the condensation from the earth's hot steam is then cooled in the cooling tower
01:52and then the cooling water is returned to the condenser again.
01:56So, during the production process or the development process, we do not take pure water from the ground.
02:05So, the water is from the condensation process only.
02:11With the operation of GHP in PLTP Kamujang,
02:14PLN currently has 22 GHP distributed in Indonesia
02:19which can produce 203 tons of green hydrogen per year.
02:23From the total production of 203, 75 tons of hydrogen will be used for the operational needs of the uprising
02:31while 128 tons will be used to support the development of the hydrogen vehicle ecosystem.
02:38From Bandung, West Java, Ade Firman Syah, IDX Channel.