Sa pagpapatuloy ng pagsilip namin sa isyu sa konstruksyon ng New Senate Building, nakita ng GMA Integrated News Research na kasama sa kontrata ang ilang mamahaling materyales para sa interior nito.
24 Oras is GMA Network’s flagship newscast, anchored by Mel Tiangco, Vicky Morales and Emil Sumangil. It airs on GMA-7 Mondays to Fridays at 6:30 PM (PHL Time) and on weekends at 5:30 PM. For more videos from 24 Oras, visit http://www.gmanews.tv/24oras.
#GMAIntegratedNews #KapusoStream
Breaking news and stories from the Philippines and abroad:
GMA Integrated News Portal: http://www.gmanews.tv
Facebook: http://www.facebook.com/gmanews
TikTok: https://www.tiktok.com/@gmanews
Twitter: http://www.twitter.com/gmanews
Instagram: http://www.instagram.com/gmanews
GMA Network Kapuso programs on GMA Pinoy TV: https://gmapinoytv.com/subscribe
24 Oras is GMA Network’s flagship newscast, anchored by Mel Tiangco, Vicky Morales and Emil Sumangil. It airs on GMA-7 Mondays to Fridays at 6:30 PM (PHL Time) and on weekends at 5:30 PM. For more videos from 24 Oras, visit http://www.gmanews.tv/24oras.
#GMAIntegratedNews #KapusoStream
Breaking news and stories from the Philippines and abroad:
GMA Integrated News Portal: http://www.gmanews.tv
Facebook: http://www.facebook.com/gmanews
TikTok: https://www.tiktok.com/@gmanews
Twitter: http://www.twitter.com/gmanews
Instagram: http://www.instagram.com/gmanews
GMA Network Kapuso programs on GMA Pinoy TV: https://gmapinoytv.com/subscribe
Category
🗞
NewsTranscript
00:00As we continue to look into the issue of the construction of the new Senate building,
00:05GMA Integrated News Research saw that some expensive materials are included in the contract for its interior.
00:12Here is the special report of Ian Cruz.
00:18In Phase 1 and 2 of the construction of the new Senate building in Taguig,
00:23the contractor is Hillmarks Construction Corporation.
00:27But if the contract for Phase 1 goes through competitive public bidding,
00:31the contract for Phase 2 is negotiated procurement or no bidding.
00:37This is the way the Senate chose to follow the timeline,
00:41to have better coordination, and to ensure responsibility and responsibility
00:48if there is only one candidate for Phase 1 and 2 of the project.
00:52DPWS Secretary Manuel Bonoan, for the Government,
00:58and Hillmarks Chairman of the Board Efren Canlas, for the Contractor,
01:03were chosen. The value of the contract is more than 2.375 billion pesos
01:08for the fit-out construction or the construction of the interior space.
01:12In looking into the contract of GMA Integrated News Research,
01:15the budget for the materials and works for the building itself was seen.
01:21The finishing and other civil works cost the most, reaching 1.45 billion pesos.
01:28For the items here, the allocation exceeded 185 million pesos
01:32for the various types of tiles.
01:35The laminated wood tiles cost the most,
01:38worth 75,000 pesos per square meter.
01:42The acoustics of the building also cost more than 142 million pesos.
01:49The acoustic louver windows cost almost 200,000 pesos per square meter.
01:57The low-emissivity insulated vision glass for the windows
02:04cost more than 100,000 pesos per square meter.
02:07The glass has a special coating so that it is not too cold or hot inside,
02:12and a pump film or additional protection in case of an attack or explosion.
02:18The glass fiber-reinforced concrete cladding panels cost almost 87 million pesos,
02:24worth almost 58,000 pesos per square meter.
02:28The new Senate will also approve six types of decorative stone
02:33worth 10 million pesos.
02:36The most expensive of these is the 57-piece Calacatta Silk Marble
02:42worth almost 54,000 pesos per square meter.
02:46The generator cost almost 262 million pesos,
02:51and almost 119 million pesos for the lighting fixtures and lamps.
02:56For the mechanical works,
02:58it will cost almost 116 million pesos for the elevator and escalator,
03:03and more than 62 million pesos for the air-conditioning.
03:07The provisional sum of 75 million pesos will also be added
03:11in case the amount or value of the items changes
03:14due to the long period of time from the design to the actual start of the project.
03:20In the Senate's review of the cost of the house,
03:24it was revealed that Phase 1 of the project is now worth 8.9 billion pesos.
03:30The contract for Phase 2 is now worth 2.375 billion pesos,
03:36while the budget for Phase 3 is now worth 10.33 billion pesos.
03:42This is not included in the purchase of the land
03:45where the house is being built in Navy Village, Taguig,
03:48which is now worth 1.649 billion pesos.
03:52The sum total for now is now worth 23.254 billion pesos.
03:57According to the DPWH,
03:59Phase 4 is still possible for the consideration of the security of the Senators.
04:04There is still no value given for this.
04:07We continue to hear the statements of Hillmarks,
04:10the DPWH and the Senators in charge of the project.
04:14For GMI Integrated News, I am Ian Cruz for Katutok 24 Horas.