• 5 months ago
Asset maintenance and replacement works at the Sungai Selangor Phase 1 Water Treatment Plant (SSP1) have reached 63.1% completion as of 3pm Wednesday (June 5), says Air Selangor.

In a press release issued at 3.30pm, Air Selangor said work was proceeding on schedule to meet the expected completion time of 7pm.

Read more at https://tinyurl.com/mpak3p3h

WATCH MORE: https://thestartv.com/c/news
SUBSCRIBE: https://cutt.ly/TheStar
LIKE: https://fb.com/TheStarOnline

Category

🗞
News
Transcript
00:00As of 3 p.m. on Wednesday, asset maintenance and replacement work at the Sungai Selangor
00:08Phase 1 Water Treatment Plant, SSP1 WTP, were proceeding as scheduled.
00:15Pengurusan I Selangor Sendrian Berhardt announced in a post on Facebook that the repair works
00:21are expected to be completed by 7 p.m.
00:25Residents in seven affected areas in the Klang Valley can expect water supply restoration
00:31to begin in stages starting at 3 a.m. on Thursday.
00:35I Selangor stated that the water supply restoration is expected to reach approximately 20 percent
00:42by 3 p.m. on Thursday and up to 90 percent by 3 a.m. the following day, with full restoration
00:49anticipated by noon on Friday.
00:53Residents are reminded that the duration of the water supply disruption and subsequent
00:58recovery will depend on their location and water pressure within the distribution system.
01:05The asset maintenance and replacement work at the plant began at 9 a.m. on Wednesday
01:11as scheduled.
01:13In May, I Selangor announced that seven areas in the Klang Valley, namely Kuala Lumpur,
01:18Gombak, Hulu Selangor, Klang, Kuala Selangor, Petaling and Shah Alam would experience scheduled
01:25water disruption from June 5 to 7 due to the maintenance and replacement work at the SSP1 WTP.
01:35For further information and updates on the scheduled water cuts, residents can check
01:40I Selangor's official communication channels or contact I Selangor at 15300.

Recommended