00:00 we'll be closing the southbound carriageway from Stockbury roundabout to around Churchill
00:06 area where the crossover is, as well as the westbound, so the London bound offslip from the M2.
00:12 So yeah, it's going to be closed for a period of five weeks, aiming to open it on the Easter
00:18 weekend. It's necessary that we have to do this due to the nature of the work that we're doing, so
00:25 we're having to reconstruct the carriageway, do a lot of drainage works, work some central
00:31 reservation and reconstruct the entire road on top of the existing carriageway, which is why
00:38 it's really difficult or next to impossible to be able to do that without having to do a closure
00:43 of this scale. We always try and find the right balance between the disruption to our customers,
00:49 so that's both people that travel through the junction but also the local communities,
00:55 with the fact that we obviously have to deliver a project efficiently with taxpayers' money and be
01:00 conscious of that. And then there's sometimes there are situations that kind of dictate a lot
01:04 of what you have to do, so like I said, in this situation, due to the nature of the work, it means
01:09 that there is very little alternative what we have to do, so then we have to find a way to do it in a
01:15 way that will cause the least disruption.