Wakil Presiden Gibran Rakabuming Raka meninjau proyek pembangunan rel layang dan underpass Simpang Joglo, di Kota Solo, Jawa Tengah, Sabtu (2/11).
Category
🗞
NewsTranscript
00:00President Gibran Raka Buming Raka visited the Elevated Railway project and the Simpang Joglo underpass in the city of Solo, Central Java on Saturday morning.
00:18Gibran announced that the underpass will be completed on December 20, 2024.
00:26Meanwhile, the Elevated Railway project will be completed on December 31, 2024.
00:32The budget for the second development of the project is sourced from the State Budget Ministry.
00:36In addition, Gibran also investigated the Gormanahan project, which collapsed several years ago.
00:42Currently, it is being re-worked using funds from the United Arab Emirates and is targeted for the coming December.
00:51There are two projects for the Simpang Joglo underpass and the Elevated Railway project.
01:00The Elevated Railway project has been in operation for about three years and is now 85% complete.
01:09For the underpass, our progress is about 78%.
01:16The underpass walls have been completed, we just need to do the excavation and reinforcements in several structures.
01:28For the underpass, we have prepared a lot of models to be imported, such as the trunk, AC, lift, single seat, all of them will be imported.
01:46There are eight of them, all of them will be imported, and Mr. Wawres hopes that they will be imported as soon as possible.
02:01The Elevated Railway and Simpang Joglo underpass project is a national strategic project and was initiated by President Joko Widodo.
02:10This project has been in operation for three years.
02:13From Solo, Central Java, I'm Yoma Suriady, Kantor Berita Antara, reporting for NET.