Determine the expected dragline production in loose cubic meter (LCM) per hour based on the following information
Dragline size = 1.5 cu.m
Swing angle = 120 deg
average depth of cut = 2.4 m
Material = common earth
Job Efficiency = 50 min/hr
Soil swell = 25%
-
paki pindot po sa "LIKE" button mga Engr.
and click SUBSCRIBE na rin po if hindi pa po kayo naka "SUBSCRIBE"
Maraming salamat po sa inyo mga Engineers and Future Engineers.
mabuhay po kayong lahat.
-
FB Page - https://www.facebook.com/MrComputerCiviLEngineer
Tiktok - https://www.tiktok.com/@SolUsmanJr
-------------
CREDIT:
-------------
Soundtrack:
Ace Attorney Dual Destinies - Apollo Justice (I'm fine)
Ace Attorney Spirit of Justice (Credit Theme)
Avatar:
SuperME Cartoon Avatar Maker (mobile app)
Reference:
"Licensure Exams for Civil Engineering" by BESAVILLA
"CE Reference for Licensure Examination" by GILLESANIA
-
#SolUsmanJr
#ceboardexam
#civilengineeringlicensureexam
Dragline size = 1.5 cu.m
Swing angle = 120 deg
average depth of cut = 2.4 m
Material = common earth
Job Efficiency = 50 min/hr
Soil swell = 25%
-
paki pindot po sa "LIKE" button mga Engr.
and click SUBSCRIBE na rin po if hindi pa po kayo naka "SUBSCRIBE"
Maraming salamat po sa inyo mga Engineers and Future Engineers.
mabuhay po kayong lahat.
-
FB Page - https://www.facebook.com/MrComputerCiviLEngineer
Tiktok - https://www.tiktok.com/@SolUsmanJr
-------------
CREDIT:
-------------
Soundtrack:
Ace Attorney Dual Destinies - Apollo Justice (I'm fine)
Ace Attorney Spirit of Justice (Credit Theme)
Avatar:
SuperME Cartoon Avatar Maker (mobile app)
Reference:
"Licensure Exams for Civil Engineering" by BESAVILLA
"CE Reference for Licensure Examination" by GILLESANIA
-
#SolUsmanJr
#ceboardexam
#civilengineeringlicensureexam
Category
๐
Learning